Excellon Resources Mobilizes Contractor and Commences Rehabilitation at Mallay Silver Mine, Peru

Rhea-AI Impact
(Neutral)
Rhea-AI Sentiment
(Neutral)
Tags

Excellon Resources (OTC:EXNRF) has initiated underground rehabilitation activities at its 100%-owned Mallay Silver Mine in Peru, marking a significant step towards resuming silver production. The company has mobilized an experienced underground mining contractor to focus on cleaning and reinforcing the main haulage levels, with rehabilitation expected to complete within four months.

The company aims to achieve nameplate capacity of 600 tpd production by Q2 2026. Key upcoming milestones include completion of an NI 43-101 Mineral Resource Estimate by August 2025, mine rehabilitation by November 2025, followed by development work, stope production preparations, and exploration drilling targeting high-grade vein extensions.

Excellon Resources (OTC:EXNRF) ha avviato le attivit脿 di riabilitazione sotterranea presso la sua miniera d'argento Mallay, di propriet脿 al 100% in Per霉, segnando un passo importante verso la ripresa della produzione di argento. L'azienda ha mobilitato un appaltatore esperto in estrazione mineraria sotterranea per concentrarsi sulla pulizia e il rinforzo dei principali livelli di trasporto, con la riabilitazione prevista entro quattro mesi.

L'obiettivo dell'azienda 猫 raggiungere una capacit脿 nominale di produzione di 600 tpd entro il secondo trimestre del 2026. I principali traguardi futuri includono il completamento di una stima delle risorse minerarie secondo lo standard NI 43-101 entro agosto 2025, la riabilitazione della miniera entro novembre 2025, seguita da lavori di sviluppo, preparativi per la produzione nelle camere di estrazione e perforazioni esplorative mirate all'estensione di vene ad alto tenore.

Excellon Resources (OTC:EXNRF) ha iniciado actividades de rehabilitaci贸n subterr谩nea en su mina de plata Mallay, de propiedad total en Per煤, marcando un paso significativo hacia la reanudaci贸n de la producci贸n de plata. La compa帽铆a ha movilizado a un contratista experimentado en miner铆a subterr谩nea para enfocarse en la limpieza y refuerzo de los niveles principales de transporte, con la rehabilitaci贸n prevista para completarse en cuatro meses.

La empresa tiene como objetivo alcanzar una capacidad nominal de producci贸n de 600 tpd para el segundo trimestre de 2026. Los hitos clave pr贸ximos incluyen la finalizaci贸n de una estimaci贸n de recursos minerales NI 43-101 para agosto de 2025, la rehabilitaci贸n de la mina para noviembre de 2025, seguida por trabajos de desarrollo, preparaci贸n para la producci贸n en c谩maras y perforaci贸n exploratoria dirigida a extensiones de vetas de alta ley.

Excellon Resources (OTC:EXNRF)電� 韼橂(鞐� 鞙勳箻頃� 100% 靻岇湢頃� Mallay 鞚甏�鞐愳劀 歆頃� 氤店惮 鞛戩梾鞚� 鞁滌瀾頄堨溂氅�, 鞚措姅 鞚 靸濎偘 鞛皽毳� 頄ロ暅 欷戩殧頃� 雼硠鞛呺媹雼�. 须岇偓电� 靾欕牗霅� 歆頃� 毂勱荡 瓿勳暯鞛愲ゼ 霃欖洂頃橃棳 欤检殧 鞖措皹 霠堧波鞚� 觳唽 氚� 氤搓皶鞐� 歆戩頃橁碃 鞛堨溂氅�, 氤店惮 鞛戩梾鞚 4臧滌洈 鞚措偞鞐� 鞕勲霅� 鞓堨爼鞛呺媹雼�.

须岇偓电� 2026雲� 2攵勱赴旯岇 鞚检澕 600韱� 靸濎偘 電ル牓 雼劚鞚� 氇╉憸搿� 頃橁碃 鞛堨姷雼堧嫟. 欤检殧 頄ロ泟 鞚检爼鞙茧電� 2025雲� 8鞗旉箤歆 NI 43-101 甏戨 鞛愳洂 韽夑皜 鞕勲, 2025雲� 11鞗旉箤歆 甏戩偘 氤店惮 鞕勲, 鞚挫柎靹� 臧滊皽 鞛戩梾, 鞀ろ啝頂� 靸濎偘 欷牍� 氚� 瓿犽摫旮� 甏戨Д 鞐办灔 韮愳偓毳� 鞙勴暅 鞁滌稊 鞛戩梾鞚� 韽暔霅╇媹雼�.

Excellon Resources (OTC:EXNRF) a lanc茅 des travaux de r茅habilitation souterraine dans sa mine d'argent Mallay, d茅tenue 脿 100 % au P茅rou, marquant une 茅tape importante vers la reprise de la production d'argent. La soci茅t茅 a mobilis茅 un entrepreneur minier souterrain exp茅riment茅 pour se concentrer sur le nettoyage et le renforcement des principaux niveaux de transport, la r茅habilitation devant 锚tre achev茅e dans un d茅lai de quatre mois.

L'objectif de l'entreprise est d'atteindre une capacit茅 nominale de production de 600 tonnes par jour d'ici le deuxi猫me trimestre 2026. Les 茅tapes cl茅s 脿 venir comprennent la r茅alisation d'une estimation des ressources min茅rales NI 43-101 d'ici ao没t 2025, la r茅habilitation de la mine d'ici novembre 2025, suivies par des travaux de d茅veloppement, la pr茅paration 脿 la production en chambres et des forages d'exploration visant l'extension de veines 脿 haute teneur.

Excellon Resources (OTC:EXNRF) hat mit den unterirdischen Sanierungsarbeiten in seiner zu 100 % im Besitz befindlichen Mallay Silbermine in Peru begonnen, was einen bedeutenden Schritt zur Wiederaufnahme der Silberproduktion darstellt. Das Unternehmen hat einen erfahrenen unterirdischen Bergbauauftragnehmer beauftragt, der sich auf die Reinigung und Verst盲rkung der Hauptf枚rderstrecken konzentriert. Die Sanierung soll innerhalb von vier Monaten abgeschlossen sein.

Das Ziel des Unternehmens ist es, bis zum zweiten Quartal 2026 eine Nennkapazit盲t von 600 Tonnen pro Tag zu erreichen. Wichtige bevorstehende Meilensteine sind die Fertigstellung einer NI 43-101 Mineralressourcensch盲tzung bis August 2025, die Bergbausanierung bis November 2025, gefolgt von Entwicklungsarbeiten, Vorbereitungen f眉r die Stollenproduktion und Erkundungsbohrungen zur Erschlie脽ung von hochgradigen Aderverl盲ngerungen.

Positive
  • Rehabilitation timeline of 4 months aligns with broader restart plan
  • Clear production target of 600 tonnes per day by Q2 2026
  • 100% ownership of the Mallay Silver Mine
  • Additional exploration potential through the Pierina vein system and Tres Cerros corridor
Negative
  • Several months required before actual production can begin
  • Resource estimate still pending, creating uncertainty about mine potential
  • Production restart timeline extends into Q2 2026, indicating significant wait for revenue generation

Toronto, Ontario--(Newsfile Corp. - July 21, 2025) - Excellon Resources Inc. (TSXV: EXN) (OTC Pink: EXNRF) (FSE: E4X2) ("Excellon" or the "Company") is pleased to have mobilized a mining contractor and commenced underground rehabilitation activities at its 100%-owned Mallay Silver Mine (the "Mallay Mine") in Peru. Excellon's plan to restart operations at the past-producing Mallay Mine and return the Company to silver production is underway.

Highlights:

  • Experienced underground mining contractor mobilized to the Mallay Mine to initiate rehabilitation, development and preparation works.

  • Initial rehabilitation efforts focused on cleaning and reinforcing the main haulage levels of the mine (4,150 and 4,090 levels), including scaling, improving ground support and ventilation, and re-opening key drifts and ramps for equipment access.

  • Rehabilitation activities are expected to be completed within four months, consistent with Excellon's broader restart plan.

  • As the rehabilitation phase advances, the Company will be positioned to further evaluate production planning, utilizing existing advanced underground development and stope preparation.

  • The current schedule keeps Excellon on track to achieve ramp up to nameplate capacity of 600 tpd production, by the second quarter of 2026.

Paul Keller, Chief Operating Officer of Excellon, commented: "Mobilizing our mining contractor and commencing site rehabilitation at Mallay marks a pivotal operational milestone for Excellon. Our team, in partnership with an experienced Peruvian contractor, is now fully engaged in safely and responsibly rehabilitating the underground workings and preparing key areas of the mine for the next phase of development. This progress underscores the Company's operational focus and commitment to executing the Mallay restart efficiently and safely, bringing Excellon closer to resuming silver production in Peru."

Next Steps and Upcoming Milestones:

Priorities over the next six months include executing a detailed Mallay restart plan and demonstrating the property-wide mineral potential beyond the existing historical resources. Key near-term milestones in the upcoming stages include:

  • Completion of NI 43-101 Mineral Resource Estimate (In Progress): Finalize updated resource estimate model for the Mallay Mine, incorporating historical data and current metal price assumptions. This work is underway and expected to be completed by late August 2025.

  • Completion of Mine Rehabilitation (In Progress): Continue rehabilitation of critical underground workings. This work is underway and expected to be completed by November 2025.

  • Advance Operational Planning: Following the updated Mineral Resource Estimate and completion of mine rehabilitation, the Company intends to advance internal mine planning and evaluate operating scenarios to support strategic decision-making and restart execution.

  • Production Restart: Following underground rehabilitation, initiate development and stope production preparations for further production guidance.

  • In-Mine Exploration Drilling: Commencement of underground drilling, targeting extensions of known high-grade veins and new mineralized zones with a goal of expanding the resource base. This work will commence upon completion of mine rehab and contemporaneously with production restart.

  • District Exploration Update: Concurrent with mine rehabilitation, exploration on high-priority targets in the immediate Mallay Mine area, including the Pierina vein system, is underway. The Company is also advancing community discussions at Tres Cerros, a 2.5 Km corridor of high-sulfidation epithermal alteration with robust surface mineralization and geophysical anomalies.

Qualified Person

Paul Keller, P.Eng., Excellon's Chief Operating Officer and a "Qualified Person" as defined by National Instrument 43-101 - Standards of Disclosure for Mineral Projects, has reviewed and approved the technical information contained in this release.

About Excellon Resources Inc.

Excellon's vision is to realize opportunities through the acquisition and advancement of quality precious and base metal assets, leveraging an experienced management team for the benefit of its employees, communities and shareholders. The Company is focused on the potential restart of the Mallay Silver Mine in Peru. Excellon also holds a portfolio of exploration-stage projects, including Kilgore, an advanced gold project in Idaho, and Silver City, a high-grade epithermal silver district in Saxony, Germany, and the Tres Cerros Gold/Silver Exploration Property in Peru, providing additional growth upside. Additional details on Excellon's properties can be found at .

For Further Information, Please Contact:

Excellon Resources Inc.
Shawn Howarth, President & Chief Executive Officer
[email protected]

Neither the TSX Venture Exchange nor its Regulations Services Provider (as that term is defined in the polices of the TSXV) has reviewed the adequacy or accuracy of this news release.

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING STATEMENTS

All statements, other than statements of historical fact, contained, referenced or incorporated by reference in this news release constitute "forward-looking statements" and "forward looking information" (collectively, "forward-looking statements") within the meaning of applicable Canadian and United States securities legislation. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as: "actively", "advance", "anticipated", "assess", "believe", "cause", "commence", "completion", "conditions", "consideration", "continues", "development", "due course", "expectation", "exploration", "extend", "extension", "flexibility", "focused", "forward", "further", "future", "if", "implement", "liquidity", "looking", "maturity", "may", "negotiations", "occur", "opportunities", "options", "outcome", "outstanding", "potential", "providing", "reach", "restructuring", "risk", "subject to", "to be", "update", "vision", "waive", "when", "will", and "would", or variations of such words, and similar such words, expressions or statements that certain actions, events or results can, could, may, should, to, will, would (or not) be achieved, occur, provide, result, complete or support in the future or which, by their nature, refer to future events. In some cases, forward-looking information may be stated in the present tense, such as in respect of current matters that may be continuing, or that may have a future impact or effect.

Forward-looking statements include statements regarding the proposed restart of the Mallay Mine; the Company's path back to production and beyond; building a foundation for potential production and discovery across the district; timing and completion of a NI 43-101 Mineral Resource Estimate; timing and completion of underground rehabilitation; timing of production restart; timing and completion of in-mine exploration drilling; anticipated drill program for Tres Cerros in 2026; and the Company's objectives, goals and future plans and strategies. Although the Company believes that such statements are reasonable, it can give no assurance that such expectations will prove to be correct, and any forward-looking statements by the Company are not guarantees of future actions, results or performance. Forward-looking statements are based on assumptions, estimates, expectations and opinions, which are considered reasonable and represent best judgment based on available facts, as of the date such statements are made. If such assumptions, estimates, expectations and opinions prove to be incorrect, actual and future results may be materially different than expressed or implied in the forward-looking statements. Forward-looking statements are inherently subject to known and unknown risks, uncertainties, contingencies and other factors which may cause the actual results or performance of the Company to be materially different from any future results or performance expressed or implied by the forward-looking statements. Such risks, uncertainties, contingencies and other factors include, among others, the inability of the Company to complete a restart of the Mallay Mine; risks related to rehabilitation, development and ramp-up of mining operations (including unanticipated costs or delays); commodity price fluctuations and global demand for silver, lead and zinc; operational and technical challenges in restarting an underground mine; regulatory and permitting risks; general economic and market conditions; the inability of the Company to complete the interest payment in Common Shares on the terms proposed or at all; the inability of the Company to complete the Debt Settlement on the terms proposed or at all; the "Risk Factors" in the Company's annual information form dated March 31, 2025 (the "2025 AIF"), and the risks, uncertainties, contingencies and other factors identified in the Company's Management's Discussion and Analysis, and accompanying financial statements, for the year ended December 31, 2024, and the Company's other applicable public disclosure (collectively, "Company Disclosure"). The foregoing list of risks, uncertainties, contingencies and other factors is not exhaustive; readers should consult the more complete discussion of the Company's business, financial condition and prospects that is provided in the 2025 AIF and the other Company Disclosure. The forward-looking statements referenced or contained in this news release are expressly qualified by these Cautionary Statements as well as the Cautionary Statements in the other Company Disclosure. Forward-looking statements contained herein are made as of the date of this news release (or as otherwise expressly specified) and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise, except as required by applicable laws.

Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

To view the source version of this press release, please visit

FAQ

When will Excellon Resources (EXNRF) complete the Mallay Mine rehabilitation?

Excellon expects to complete the mine rehabilitation by November 2025, approximately four months from the start of work.

What is the production capacity target for Excellon's Mallay Silver Mine?

Excellon aims to achieve a nameplate capacity of 600 tonnes per day (tpd) by the second quarter of 2026.

When will Excellon Resources release the NI 43-101 Resource Estimate for Mallay?

The updated NI 43-101 Mineral Resource Estimate is expected to be completed by late August 2025.

What are the key rehabilitation activities at Excellon's Mallay Mine?

The rehabilitation focuses on cleaning and reinforcing the main haulage levels (4,150 and 4,090 levels), including scaling, improving ground support and ventilation, and re-opening key drifts and ramps for equipment access.

What exploration opportunities exist at Excellon's Mallay property?

Excellon is exploring the Pierina vein system and the Tres Cerros corridor, which features 2.5 km of high-sulfidation epithermal alteration with surface mineralization and geophysical anomalies.